Translated summaries of Hebrew and English coverage, each linking out to the original source.
September 2026
INFRASTRUCTURE
A ₪217 million underground substation goes live for north Tel Aviv and Sde Dov
Maariv: the Israel Electric Corporation has connected a new underground substation to the grid at a cost of about ₪217 million, a project Maariv ties to the construction coming in the Sde Dov district. It has two 75 MW transformers, sits about 20 metres underground, took about four years to build, and will serve Ramat Aviv, Tel Aviv University and the rest of north Tel Aviv.
Aviv-Melisron lot 3205 design plan approved: 320 homes and a 40-storey tower
Rova Sde Dov: the Tel Aviv-Jaffa planning subcommittee approved the architectural design plan for North-complex lot 3205, promoted by Aviv-Melisron as "Aviv in Sde Dov". The plan has 320 homes, about 3,800 sqm of employment space and about 1,000 sqm of commerce on a lot of about 6 dunams, with a 40-storey tower. Miloslavsky Architects prepared the plan.
Fuel-tank park design plan approved at the Yarkon mouth
Rova Sde Dov: the Tel Aviv-Jaffa local planning committee approved the design plan for Fuel Tank Park at the Yarkon mouth and recommended it to the district committee and the coastal environment committee. The historic IEC tanks across the Yarkon had already become a night-lit landmark; the winning conversion plan was selected in May 2026.
Globes: how many Sde Dov homes actually sold in the first half of 2026
Globes: seven projects are now marketing in the district, with first occupancy still expected in 2029. RAINBOW sold 7 homes in the first half of 2026, 3 of them in the second quarter, against 59 in all of 2025 and 99 in 2024, and DIMRI YAMA had sold about 41 of its 458 homes. Hagag's sales and marketing costs rose to ₪10.8 million in the half, from ₪4.2 million a year earlier.
Court halts the Big Bloc rights lottery over Sde Dov soil contamination
Ynet: the Herzliya Magistrates Court ruled the compound lottery must not proceed for now, on the concern that differences in contamination, clean-up cost and delay between compounds would skew their values and divide rights worth billions of shekels unevenly. Globes: Adam Teva V'Din opposes striking the contamination petition despite the High Court's recommendation.
Private landowners tell the court a lottery before contamination tests is unfair
Globes: contamination fears continue to hold up the division of rights among about 1,700 Big Bloc landowners. After the assessor found no new information justifying a change to how value is split between compounds, rights holders argue the absence of contamination results is precisely why the lottery cannot yet be held.
Gindi to sell VOGUE commercial and employment space to REIT 1 for about ₪400 million
Rova Sde Dov: Gindi Holdings said it signed with REIT 1 to sell all of the commerce and employment space in VOGUE in Central Sde Dov for about ₪400 million. The package is about 5,000 sqm of commerce, about 7,400 sqm of employment, and 127 attached parking spaces, the project's entire income-producing component.
Contamination tests overrun, and the Big Bloc managers now want the lottery to go ahead
Globes: testing the state told the court in May would take 60 to 90 days is still not finished, and even the sampling plans are still awaiting Environment Ministry approval. The Big Bloc land managers, who asked in May for the compound lottery to be delayed, now ask the court to let it go ahead rather than wait months more.
DIMRI YAMA records no Q2 sales; remaining inventory marked down to ₪62,000/sqm
Calcalist: YAMA sold none in Q2 (about 40 of 458 units, ~8%). Globes: remaining inventory cut from ₪67,000 to ₪62,000 per sqm, with PFAS soil removal underway under the Environment Ministry.
The Land Authority has no contamination findings to show yet, and buyers seek ₪1.55 million back
Globes: the Israel Land Authority told the court its contamination tests are progressing but has published no findings or mapping, so the division of the Big Bloc land is still stuck. Rights holders say the uncertainty is hurting deals. Separately, apartment buyers are seeking to cancel option agreements and recover about ₪1.55 million, saying they were not told about the contamination when they signed.
ILA delays the Big Bloc land lottery pending contamination tests
The Herzliya court had already moved the private-owners lottery from late June to 11 August. Globes: ILA's update still has no plot-by-plot pollution map, sampling plans await Environment Ministry approval, and the draw is delayed again.
Levi Eshkol bridge works begin, linking the Eshkol complex to Yarkon Park
Construction started on the Levi Eshkol bridge over Rokach Boulevard, a pedestrian and cycle crossing that gives north-west Tel Aviv a direct route into Yarkon Park and its path network. It is expected to serve Kochav HaTzafon, Tochnit Lamed, Nofei Yam and Ramat Aviv HaHadasha.
Eshkol lot 303 design plan conditionally approved: about 26,000 sqm of employment and commerce
Rova Sde Dov: the Tel Aviv-Jaffa planning subcommittee conditionally approved the design and development plan for lot 303 in the Eshkol complex, two nine-storey buildings for employment and commerce on Ibn Gvirol Street, beside the linear park and near the future Zahara Levitov light-rail station. Approval depends on review by the city engineer.
Nofei Yam Tzafon, a planned 1,500-home neighbourhood just north of Sde Dov, moves forward
ice: planning is advancing for Nofei Yam Tzafon (plan TA/5091), about 1,500 homes on land just north of the Sde Dov district between Levi Eshkol, Propes and Ibn Gvirol streets. The plan area has been cut from about 190 to about 150 dunams to make room for more public space, about a quarter is planned for commerce, it includes affordable housing, and a deposit-stage hearing is expected around July 2027.
Buyers in Sde Dov projects are writing cancellation clauses into their contracts
Globes: apartment buyers in district projects are adding cancellation clauses to purchase contracts because of the PFAS findings. The Environment Ministry told Globes that all nine plots with PFAS indications are earmarked for housing and that sampling results will be published once the investigation reports are approved. Globes names Dimri, Shikun & Binui, Gindi Holdings, Mivne and Prashkovsky among the companies involved; some developers say the ministry has already confirmed that their land is clean.
The nine Sde Dov plots with PFAS indications are named for the first time
Globes: the Environment Ministry named the nine plots where PFAS indications were found: 103, 105, 106, 107, 301, 303, 2206, 2207 and 2102. Globes matched them to developers, among them lot 103 (Nahmias, UTOPIA), lot 107 (Y.H. Dimri, DIMRI YAMA), lot 2206 (Gindi Holdings), lot 106 (Shikun & Binui), lots 2207 and 2102 (Prashkovsky) and lot 301 (Hadas Capital). The ministry said results will be published once the investigation reports are approved.
Three seafront plans approved in the North complex: lots 3101, 3105 and 3106, 332 homes
Rova Sde Dov: the Tel Aviv-Jaffa planning subcommittee approved the design and development plans for lots 3101, 3105 and 3106, on the district's westernmost line beside the coastal park. Together they have 332 homes plus commerce, internal courtyards, public passages and shared facilities for residents. The report does not name the developers.
Green Line works progress: when will the train reach Sde Dov?
A municipal update on the Green Line, including a southern-section timetable presented by Mayor Huldai. Four stations will serve the district.
via District records
ENVIRONMENT
The same contamination has been found beyond Sde Dov, at Glilot, Sirkin and other sites
Globes: a letter from the Water Authority's director-general to the Israel Land Authority lists other sites where similar PFAS contamination has been found or is suspected, including Sirkin Camp in Petah Tikva, the Kiryat Chaim terminal, the Glilot area, former and current airfields, fuel farms and power stations. The authority says it has mapped PFAS at risk sites systematically since it analysed Sde Dov groundwater in 2022.
Lot 2207 design plan approved: Prashkovsky's 410 long-term rental homes
Rova Sde Dov: the Tel Aviv-Jaffa planning subcommittee approved the design plan for lot 2207 in the centre of the district, a long-term rental project by Prashkovsky Meniv on Ibn Gvirol, Einstein and Batya Lishansky streets. It has 410 rental homes, 205 of them at controlled rents.
Israel Brothers lot 2103 design plan approved: 424 apartments, 45- and 25-story towers
Tel Aviv's local committee approves Israel Brothers' Central lot 2103: 424 homes (348 in two towers, 76 in 5- and 8-story fabric buildings), about 1,766 sqm of retail, architect Moshe Tzur.
FIRST passes ₪1.6 billion in sales: 191 of 350 homes sold
Ynet: Hagag Group's first-quarter 2026 report shows FIRST sold 59 homes in the five months to the report, for about ₪426 million, taking it to 191 of its 350 homes, 55% of the project, for more than ₪1.6 billion in under a year of marketing.
Listed Sde Dov prices hold at ₪75,000 to ₪85,000 per sqm, but financing offers hide a discount
Bizportal: developers' first-quarter 2026 filings show a slowing sales pace and financing offers worth a hidden 6 to 8% off the listed price. Israel Canada reported an average of about ₪85,700 per sqm including VAT. ZOHI reported a headline average of ₪64,700 per sqm, which falls to about ₪60,900 once the financing discount is taken out.
Israel Canada's sales rose in the first quarter, but RAINBOW sold four homes
Globes: Israel Canada sold 86 apartments across the company in the first quarter of 2026, up from 76, but only 4 at RAINBOW, for about ₪22 million. RAINBOW's average price since launch reached ₪81,782 per sqm at the end of the quarter, against ₪81,704 at the end of 2025 and ₪80,493 at the end of 2024.
437 homes and a 45-storey tower: SEVEN SEAS design plan approved for lot 2208
Ynet: the Tel Aviv-Jaffa local committee approved the design plan for SEVEN SEAS by Electra Residence and Dan Real Estate on Central lot 2208: 437 homes in towers of 45 and 20 storeys, with about 3,500 sqm of employment space and 2,200 sqm of commerce.
Court postpones the Big Bloc compound lottery to 11 August over contamination
Globes: the Herzliya Magistrates Court postponed the Big Bloc compound lottery, which was due the following month, to 11 August 2026, after the land managers asked for time to learn the extent of the PFAS contamination and who pays for the clean-up. The court set the same date for the Israel Land Authority to report on its testing, in line with the state's own estimate of 60 to 90 days.
The state tells the court it never committed to paying for the clean-up
Calcalist: responding in the Herzliya Magistrates Court, the Israel Land Authority and the Environment Ministry rejected the Big Bloc managers' position that the state must fully fund the PFAS investigation and clean-up, saying no formal, binding commitment on funding was ever made.
Glanor wins the tender for the district's phase A infrastructure works
mako: Glanor Group won the joint Tel Aviv municipality and Mei Avivim tender to be main contractor for the phase A development works across the roughly 1,500-dunam site: roads, water, drainage, sewage, electricity and communications, preparing the lots already sold to developers for construction.
The environment minister acknowledges a PFAS risk in the sea and on the beach near Sde Dov
Ynet: Environmental Protection Minister Idit Silman acknowledged a health risk from PFAS to bathers and to anyone in contact with groundwater at the beach near Sde Dov, while saying the area is not a drinking-water source. She wrote that the Water Authority first passed preliminary findings to the ministry at the end of 2022 and found PFAS in sea water near the beach in March 2024.
Big Bloc managers ask the court to settle who pays for the PFAS clean-up
Calcalist: the Big Bloc land managers asked the court to hold a hearing on the funding and timetable of the PFAS clean-up before the division of rights goes on, with every responsible state body present. Appraiser Roni Brill said she is already hearing from Sde Dov apartment and option buyers who want to cancel.
Calcalist: FIRST drove Hagag's 2025 results, and the dependence adds risk
Calcalist: Hagag Group's net profit rose 29% in 2025, largely on FIRST, while marketing costs nearly doubled and four sales were cancelled, three of them at Sde Dov. The company's own accounts put the lot 2270 land at ₪803 million plus ₪67 million of purchase tax, against the ₪756 million reported at the February 2025 tender.
Turnaround on soil contamination after a dramatic update of threshold values
Updated national PFAS thresholds change how findings on the old airfield are read, a potential break in the contamination saga.
via District records
ENVIRONMENT
Shomrim: a change to PFAS thresholds made the Sde Dov findings compliant
Shomrim: the Environment Ministry issued what read as a technical update to its PFAS soil thresholds, reviewed by the private firm Ecolog Engineering, which in effect made the exceedances found at Sde Dov compliant and weakened the precautionary policy. A source quoted by the outlet suspects the real purpose was to clear the district's land.
Nine building permits issued in the district so far, seven of them for excavation only
TheMarker: the Tel Aviv municipality has issued nine building permits in the Sde Dov district, two full permits and seven for shoring and excavation only. City engineer Udi Carmeli told the planning committee that soil had been removed from some plots where PFAS contamination was suspected.
~NIS 6B: the Sde Dov billion-shekel tenders were cut almost in half
Central-district winners are named for 4,191 units and about ₪6B: land about 40% cheaper than the 2021 record. Gindi, Hagag, Electra + Dan, Luzon Ronson, Israel Brothers, and A.A.I. Abu + Tomer Koko are on the list.