## ASHIRA

- **Developer:** Avisror Moshe & Sons
- **Lot:** 101
- **Homes:** 406
- **Status:** Full building permit March 2026; shoring and foundations complete and basement slab under way; completion expected 2030
- **Full page:** https://shavnu.com/ru/projects/ashira.md

## RAINBOW Tel Aviv

- **Developer:** Israel Canada
- **Lot:** 111
- **Homes:** 459
- **Status:** Under construction by Ashtrom since January 2026; 275 of 459 homes sold by August 2026
- **Full page:** https://shavnu.com/ru/projects/rainbow.md

## UTOPIA

- **Developer:** Nahmias Group
- **Lot:** 103
- **Homes:** 337
- **Status:** Under construction since October 2025; the developer targets handover about 40 months from October 2025
- **Full page:** https://shavnu.com/ru/projects/utopia.md

## DIMRI YAMA TLV

- **Developer:** Y.H. Dimri
- **Lot:** 107
- **Homes:** 458
- **Status:** Marketing since December 2025 under an excavation and shoring permit; 40 of 458 homes sold at 30 June 2026
- **Full page:** https://shavnu.com/ru/projects/dimri-yama.md

## ZOHI Tel Aviv

- **Developer:** Levinshtein Group, Metropolis (Allied Real Estate), Mivne Group
- **Lot:** 110
- **Homes:** 230
- **Status:** Pre-sales since January 2026; works on site begun; 63 contracts signed by 30 June 2026; occupancy expected in the second half of 2030
- **Full page:** https://shavnu.com/ru/projects/zohi.md

## GINDI VOGUE

- **Developer:** Gindi Holdings
- **Lot:** 2206, 2255
- **Homes:** 708
- **Status:** Marketing since June 2025; more than 600 contracts; penthouses and a new release on sale in 2026; occupancy expected five to seven years from August 2026
- **Full page:** https://shavnu.com/ru/projects/gindi-vogue.md

## FIRST by Hagag

- **Developer:** Hagag Group
- **Lot:** 2270
- **Homes:** 350
- **Status:** Design plan approved March 2026; building permit in process; marketing; 179 of 350 homes unsold after the second quarter of 2026
- **Full page:** https://shavnu.com/ru/projects/first.md

## SEVEN SEAS

- **Developer:** Electra Residence and Dan Real Estate (Nahor), Dan Real Estate
- **Lot:** 2208
- **Homes:** 437
- **Status:** Selling since December 2025; design plan approved 20 May 2026; no sales figure published after March 2026
- **Full page:** https://shavnu.com/ru/projects/seven-seas.md

## Luzon Ronson, lot 2227

- **Developer:** Luzon-Ronson
- **Lot:** 2227
- **Homes:** 340
- **Status:** Selling since the fourth quarter of 2025; 13 conditional contracts for ₪132.4M by the first-quarter 2026 report; design plan approved 21 January 2026; land handover scheduled for the first quarter of 2027; no brand name published
- **Full page:** https://shavnu.com/ru/projects/luzon-ronson-2227.md

## Aviv BeSde Dov

- **Developer:** Aviv by Melisron
- **Lot:** 3205
- **Homes:** 320
- **Status:** Design plan approved 2 September 2026; no sales; company forecasts construction from 2028
- **Full page:** https://shavnu.com/ru/projects/aviv-sde-dov.md

## Palace Sde Dov

- **Developer:** Azrieli Group
- **Lot:** 2104
- **Homes:** 320
- **Status:** Senior living; design plan approved 18 February 2026; company expects completion in 2030; no deposit price list published
- **Full page:** https://shavnu.com/ru/projects/palace-sde-dov.md

## Prashkovsky Sde Dov (long-term rental)

- **Developer:** Prashkovsky
- **Lot:** 2102, 2203, 2207
- **Homes:** 966
- **Status:** Long-term rental, not for sale; design plans approved 21 January 2026 (2102, 2203) and 17 June 2026 (2207)
- **Full page:** https://shavnu.com/ru/projects/prashkovsky-sde-dov.md

## Sde Dov by Israel Brothers

- **Developer:** Israel Brothers
- **Lot:** 2103
- **Homes:** 424
- **Status:** Design plan approved 3 June 2026; listed by the company as a future project; no prices or sales
- **Full page:** https://shavnu.com/ru/projects/israel-brothers-sde-dov.md

## Gindi Sde Dov

- **Developer:** Chen & Itay Gindi
- **Lot:** 3107
- **Homes:** 82
- **Status:** Land won 26 March 2025. The company lists the project as coming soon and in planning, with a waiting list (page updated 28 September 2026). No design plan approval reported as of 28 September 2026.
- **Full page:** https://shavnu.com/ru/projects/chen-itai-gindi-3107.md


---

Source: https://shavnu.com/ru/projects на Shavnu, независимом гиде на русском по
району Сде Дов в Тель-Авиве. Цифры из открытых данных: отчётность налоговой
службы Израиля, ГИС Тель-Авива, тендеры и ивритская пресса.