# Sde Dov soil report, lot 303: what it shows a buyer

> The first published Sde Dov soil report, for lot 303, found PFOS above the direct-contact threshold in all 16 boreholes. Remediation cost stays open.

Canonical: https://shavnu.com/blog/the-first-published-sde-dov-soil-report-read-line-by-line

---

**Published:** 2026-10-19  
**Category:** environment  
**Reading time:** 9 minutes

**Developers covered:** Gindi Holdings, Prashkovsky, Hadas Capital

## What does the first published Sde Dov soil report actually show?

The first published Sde Dov soil contamination report, for lot 303, found PFOS above the report's direct-contact threshold in all 16 boreholes, with the worst reading almost 600 times that threshold, according to Lodan Environmental Technologies' survey for the Ministry of Environmental Protection, published 6 October 2026. It covers one commercial lot and settles neither remediation cost nor construction status.

This is the first lot-level Sde Dov soil report the Ministry of Environmental Protection has put online, and it is the clearest public account yet of what these documents contain. PFAS, short for per- and polyfluoroalkyl substances, is a family of synthetic chemicals once common in firefighting foam; they resist breaking down in soil and water, which is why regulators call them "forever chemicals." The report measured three PFAS compounds: PFOS (perfluorooctane sulfonate), PFOA (perfluorooctanoic acid) and PFHxS (perfluorohexane sulfonic acid). Lodan's team sampled lot 303 in early May 2026, then compared those results against Sde Dov threshold values that the ministry updated the following month, in June 2026, according to TheMarker's 14 October 2026 report.

## Inside the lot 303 investigation: boreholes, depths and threshold breaches

Nadlan Center's 15 October 2026 report breaks the lot 303 findings down by borehole, depth and compound rather than stopping at one headline multiple. Sixteen boreholes were drilled across the 5.6-dunam site, as reported by TheMarker (a dunam is roughly 1,000 square metres, the standard Israeli land measurement). PFOS exceeded the direct-contact threshold in every one of the 16 boreholes, PFOA exceeded it in 15, and PFHxS turned up in five, according to Nadlan Center's account of the report.

The worst PFOS reading on lot 303, 3.78 million nanograms per kilogram at half a metre depth, is almost 600 times the 6,321.4 ng/kg threshold the report uses for direct soil contact, TheMarker reported.

Borehole 7 also showed very high PFOS concentrations at one metre and two metres depth, TheMarker reported, though the outlet did not publish exact figures for those two readings.

Four of the 16 boreholes sat in an area the ministry had already flagged as suspect; the other 12 did not, according to TheMarker. PFOS exceedances turned up in both groups. TheMarker read that spread as a sign the contamination may extend beyond the former airfield's originally flagged zones, not just sit inside them. The project plans excavation to about 20 metres, according to Nadlan Center, which means any contaminated layer at depth, not only near the surface, will have to be handled during construction.

****

| Borehole | Depth | Compound | Measured concentration | Exceedance | Source |
| --- | --- | --- | --- | --- | --- |
| Borehole 7 | 0.5 m | PFOS | 3.78 million ng/kg | ~600x threshold (6,321.4 ng/kg) | TheMarker |
| Not identified | Not published | PFOS | Not published | 233x threshold | TheMarker |
| Not identified | Not published | PFOS | Not published | 174x threshold | TheMarker |
| 15 of 16 boreholes | Various | PFOA | Not published | Threshold exceeded | Nadlan Center |
| 5 of 16 boreholes | Various | PFHxS | Not published | Detected, no threshold comparison published | Nadlan Center |

## Which Sde Dov lots did the Environment Ministry name, and what does that mean?

A lot being named is not the same as a lot being investigated, and neither is the same as a lot being cleared. Naming means the ministry has identified PFAS-related findings at some stage of testing; investigation means a full report has been produced and, in lot 303's case, published; clearance means the ministry has approved a completed survey as showing no exceedance. The Ministry of Environmental Protection told Globes, in a report published 23 July 2026 and updated 26 July, that nine Sde Dov lots had completed soil investigations with PFAS-related findings: 103, 105, 106, 107, 301, 303, 2206, 2207 and 2102.

Globes reported that all nine sit under planned residential projects, even though lot 303 itself is commercial. Developer responses to Globes varied sharply. Claude Nehmias, building on lot 103, told Globes that 26 samples showed no exceedance and the ministry approved the survey in writing. Shikun Binui, on lot 106, told Globes the ministry accepted its survey in March 2026 and issued a building permit. Prashkovsky told Globes that lot 2102 was fully tested with no contamination found and ministry approval received, while testing on lot 2207 continued. Demri, on lot 107, told Globes that over 98% of its samples came back clean and under 2% of the soil had needed removal. Gindi Holdings told Globes it had not yet taken possession of lot 2206 and was awaiting instructions. The ministry told Globes it would publish sampling results for all nine lots once their reports are approved.

## Is lot 303 a housing plot, and why does a commercial lot's report matter to a home buyer?

Lot 303 is Mivne Real Estate's employment and retail lot in the Eshkol complex, not a residential site, so its findings do not transfer directly to the homes being built on the district's other named lots. Mivne bought the 5.6-dunam parcel in the Israel Land Authority's December 2024 tender for about ₪112.5 million, plus roughly ₪19.5 million in development costs, to build about 19,000 square metres of employment space and 7,300 square metres of retail, according to TheMarker's 14 October 2026 report.

What makes lot 303 relevant to a home buyer is sequencing, not use class. It is the only one of the nine named lots with a published, line-by-line investigation report as of this writing. Several of the other eight carry housing projects from companies including Shikun Binui, Prashkovsky, Demri, Gindi Holdings, Hadas Capital and Claude Nehmias, per Globes. Until their own reports are published and approved, lot 303 is the only public template a buyer can use to understand what a Sde Dov soil file actually contains.

## Does the lot 303 report mean construction stops, or who pays to clean it up?

The published report sets no remediation cost, does not say building halts, and does not specify what steps come next, according to Nadlan Center's 15 October 2026 reporting on the document. That is a narrower claim than headline coverage of the "almost 600 times" figure might suggest. The report is a measurement, not a ruling.

Cost is equally unsettled at the ministry level. Calcalist reported that the Ministry of Environmental Protection told it there is no overall estimate of expected remediation costs across Sde Dov, because costs depend on site-specific conditions and each lot's own survey findings. Mivne's own position, given to Nadlan Center, is that the state presented the land as meeting required standards at the time of purchase, and that if treatment proves necessary, clean-up and disposal costs would be negligible against the project's total cost. TheMarker's own analysis suggested the finding could add several million shekels to development costs and, separately, could feed a legal dispute if Mivne or other developers argue the state bears responsibility for contamination it created. Who ultimately pays is not settled in the public record as of this writing.

## What should a buyer ask for on a named Sde Dov lot before signing?

A buyer weighing an off-plan home on one of the nine named lots has four concrete documents to request before signing, not a general reassurance about district-wide progress.

The lot's own investigation report. A ministry-wide PFAS story tells a buyer nothing about their specific lot. Ask whether a report like the lot 303 one has been completed, and if so, whether it has been published on the ministry's site.

The ministry's approval status for that lot, not the district. Some developers named by Globes, including Shikun Binui on lot 106 and Prashkovsky on lot 2102, say the ministry has approved their surveys in writing. Ask for that written approval, not a verbal assurance.

Written confirmation of who pays for disposal. The lot 303 case shows the published record does not yet resolve this question even for the one lot with a finished report, according to Nadlan Center. A buyer should ask the developer directly, in writing, who bears disposal and remediation cost if contamination is confirmed on their lot.

The contract's delay clauses tied to environmental works. Excavation to about 20 metres on a contaminated lot, as planned for lot 303 according to Nadlan Center's report, is a different construction problem from excavation on clean ground. Check whether the contract treats environmental remediation as a force majeure event, a clause that excuses a party from delay penalties when extraordinary circumstances outside its control cause the delay, or as an ordinary developer delay that still carries financial penalties.

This checklist sits inside a wider timing question many Sde Dov buyers are already weighing: whether the district's land prices and delivery risk currently favour buying now or waiting, covered in the case for and against buying into Sde Dov in 2026.

## How much contaminated soil is in Sde Dov, and when are the Big Bloc results due?

Industry estimates cited by Calcalist put contaminated soil across Sde Dov at roughly 200,000 tonnes, against a state pilot that has so far processed just 600 tonnes of soil brought in from Ashdod. Calcalist reported on 7 September 2026 that the pilot, Israel's first attempt at PFAS soil washing, mixes contaminated soil with water and chemicals to separate out the pollutant, recovering about 95% of the soil for reuse and sending the remaining 5% to disposal. The ministry told Calcalist it had no overall estimate of remediation cost or timeline, since both depend on site-by-site survey results.

A separate deadline applies to Sde Dov's privately owned land. The Israel Land Authority told Herzliya Magistrate's Court on 6 October 2026 that drilling was complete across most of the Big Bloc, the large privately held parcel tied to a long-running ownership dispute, and that soil test results were expected within about 30 days, with a court-ordered update due by 5 November 2026. Buyers tracking dates that matter for Sde Dov decisions, tax deadlines and permit steps included, can cross-check this one against the full 2027 Sde Dov date calendar. Anyone specifically weighing a private-land purchase tied to the Big Bloc should read what that structure requires before signing in the guide to buying Sde Dov land from a private owner.

The district's PFAS and soil contamination guide on this site holds the formal thresholds and the legal framework behind these figures; this piece has focused on what one published report and one pilot programme actually show, not on restating those rules.

## Frequently asked questions

What is PFAS, and why is it called a 'forever chemical'?

PFAS, short for per- and polyfluoroalkyl substances, is a family of synthetic chemicals once common in firefighting foam, Teflon coatings and water-resistant packaging. They resist breaking down in soil and water, which is why regulators call them forever chemicals. Tivcho's chief executive told Calcalist in September 2026 that PFAS is highly carcinogenic even at low concentrations, a reason sites such as lot 303 in Sde Dov are measured against strict direct-contact thresholds rather than simple presence or absence.

How did regulators first detect PFAS contamination in Sde Dov?

The Ministry of Environmental Protection and the Israel Land Authority jointly disclosed preliminary indications of PFAS in Sde Dov's groundwater and soil in February 2026, according to Globes. That early warning came months before any lot-level report existed and led to the site-specific surveys that followed, including Lodan Environmental Technologies' investigation of lot 303, published 6 October 2026, and the ministry's July 2026 list of nine named lots.

Does the state's Ashdod soil-washing pilot solve Sde Dov's contamination problem?

Not on its own. The pilot Calcalist reported on 7 September 2026 has processed 600 tonnes of PFAS-contaminated soil brought from Ashdod, against an industry estimate of roughly 200,000 tonnes of contaminated soil across Sde Dov. The washing method recovers about 95% of treated soil for reuse and sends the remaining 5% to disposal, but the Ministry of Environmental Protection told Calcalist it has no overall timeline or cost estimate, since both depend on each lot's own survey results.

Why does it matter that lot 303 was sampled before the threshold update?

The lot 303 result was checked against a stricter yardstick than existed when the samples were taken. Lodan Environmental Technologies sampled the site in early May 2026, then measured those results against Sde Dov threshold values the Ministry of Environmental Protection updated the following month, in June 2026, according to TheMarker's 14 October 2026 report. A looser threshold at sampling time could have produced a smaller headline multiple than the nearly 600-fold exceedance eventually published.

When will the Environment Ministry publish soil reports for the other eight named Sde Dov lots?

No firm date has been published. The Ministry of Environmental Protection told Globes, in a report published 23 July 2026 and updated 26 July, that it would publish sampling results for all nine named lots once each report is approved, without giving a schedule. As of lot 303's publication on 6 October 2026, it remained the only one of the nine with a completed, public investigation report.

Why does lot 303's planned 20-metre excavation matter for PFAS cleanup?

Excavating a contaminated lot to 20 metres means any PFAS sitting deep in the ground, not just near the surface, has to be identified and handled during construction, not after. The lot 303 project plans excavation to roughly that depth, according to Nadlan Center's 15 October 2026 report, and borehole 7 showed very high PFOS concentrations at one metre and two metres as well as half a metre. Deep contamination raises the volume of soil that may need treatment or removal before building can proceed.


---

Source: https://shavnu.com/blog/the-first-published-sde-dov-soil-report-read-line-by-line on Shavnu, an independent English guide to the
Sde Dov district in Tel Aviv. Figures come from the public record: Israel Tax
Authority transaction reports, Tel Aviv GIS, tender results and the Hebrew press.